20200118-EU 05/20/2020 PSC-2020-0165-PAA-EU
PAA Order PSC-2020-0165-PAA-EU approving amended joint motion modifying weighted average costs of capital methodology; if no timely protest order to become final and effective on issuance of CO and docket to be closed; protest due 6/10/20.
Amended unopposed joint motion to modify Order PSC-2012-0425-PAA-EU regarding weighted average cost of capital methodology.
20200065-EI 05/19/2020 PSC-2020-0164-PCO-EI
Order PSC-2020-0164-PCO-EI procedural order.
Petition for a limited proceeding to eliminate accumulated amortization reserve surplus for intangible software assets, by Tampa Electric Company.
20200070-EI 05/18/2020 PSC-2020-0161-PCO-EI
Order PSC-2020-0161-PCO-EI denying OPC's motion to compel discovery.
Review of 2020-2029 Storm Protection Plan pursuant to Rule 25-6.030, F.A.C., Gulf Power Company.
20200071-EI 05/18/2020 PSC-2020-0162-PCO-EI
Order PSC-2020-0162-PCO-EI denying OPC's motion to compel discovery.
Review of 2020-2029 Storm Protection Plan pursuant to Rule 25-6.030, F.A.C., Florida Power & Light Company.
20200064-EI 05/19/2020 PSC-2020-0163-PCO-EI
Order PSC-2020-0163-PCO-EI acknowledging intervention by OPC; parties shall furnish copies of all testimony, exhs, pleadings, and other documents filed in this docket to OPC/Kelly.
Petition for a limited proceeding to approve fourth SoBRA, by Tampa Electric Company.
20200064-EI 05/19/2020 PSC-2020-0164-PCO-EI
Order PSC-2020-0164-PCO-EI procedural order.
Petition for a limited proceeding to approve fourth SoBRA, by Tampa Electric Company.
20200067-EI 05/19/2020 PSC-2020-0164-PCO-EI
Order PSC-2020-0164-PCO-EI procedural order.
Review of 2020-2029 Storm Protection Plan pursuant to Rule 25-6.030, F.A.C., Tampa Electric Company.
20200109-EQ 05/22/2020 PSC-2020-0166-PAA-EQ
PAA Order PSC-2020-0166-PAA-EQ approving FPUC’s standard offer contract and schedule; If no protest order to become final and effective on issuance of a CO; if order becomes final, docket to be closed; protest due 6/12/20.
Petition for approval of standard offer contract, by Florida Public Utilities Company.
20200092-EI 05/19/2020 PSC-2020-0164-PCO-EI
Order PSC-2020-0164-PCO-EI procedural order.
Storm protection plan cost recovery clause.
20200145-EI 05/19/2020 PSC-2020-0164-PCO-EI
Order PSC-2020-0164-PCO-EI procedural order.
Petition to approve the 2020 settlement agreement by Tampa Electric Company.
WATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20190118-WU 05/22/2020 PSC-2020-0167-PAA-WU
PAA Order PSC-2020-0167-PAA-WU approving increase in water rates for Lighthouse and order requiring four-year rate reduction and proof of adjustments of books and records; if no protest order to become final and effective on issuance of a CO; if order becomes final, docket to remain open for staff’s verification that revised tariff sheets and customer notice have been filed by Lighthouse and approved by staff, and Lighthouse has notified staff that adjustments for all the applicable NARUC USOA primary accounts have been made; once these actions are complete, docket to be closed administratively; protest due 6/12/20.
Application for increase in water rates in Gulf County by Lighthouse Utilities Company, Inc.
WATER AND WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20190166-WS 05/22/2020 PSC-2020-0168-PAA-WS
PAA Order PSC-2020-0168-PAA-WS approving increase in water rates for HC Waterworks and order requiring four-year rate reduction and proof of adjustments of books and records; if no protest order to become final and effective on issuance of a CO; if order becomes final, docket to remain open for staff’s verification that revised tariff sheets and customer notice have been filed by HC Waterworks and approved by staff, and HC Waterworks has notified staff that adjustments for all the applicable NARUC USOA primary accounts have been made; once these actions are complete, docket to be closed administratively; protest due 6/12/20.
Application for increase in water rates in Highlands County by HC Waterworks, Inc.