DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20190001-EI 10/16/2019 PSC-2019-0416-CFO-EI
Order PSC-2019-0416-CFO-EI granting Duke Energy’s request for confidential classification (of DN 08952-2019, x-ref DN 08574-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0417-CFO-EI
Order PSC-2019-0417-CFO-EI granting Duke Energy’s motion for temporary protective order (DN 08956-2019).
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0418-CFO-EI
Order PSC-2019-0418-CFO-EI granting Duke Energy’s motion for temporary protective order (DN 08770-2019).
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0419-CFO-EI
Order PSC-2019-0419-CFO-EI granting Duke Energy’s motion for temporary protective order (DN 08704-2019).
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0420-CFO-EI
Order PSC-2019-0420-CFO-EI granting Duke Energy’s motion for temporary protective order (DN 08594-2019).
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0421-CFO-EI
Order PSC-2019-0421-CFO-EI granting Duke Energy’s request for confidential classification (of DNs 06046-2019, 06052-2019 and 07512-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0422-CFO-EI
Order PSC-2019-0422-CFO-EI granting Duke Energy’s request for confidential classification (of DN 06193-2019) for a period of 24 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0423-CFO-EI
Order PSC-2019-0423-CFO-EI granting Duke Energy’s request for confidential classification (of DN 09061-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0424-CFO-EI
Order PSC-2019-0424-CFO-EI granting Duke Energy’s request for confidential classification (of DN 08671-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0425-CFO-EI
Order PSC-2019-0425-CFO-EI granting Duke Energy’s request for confidential classification (of DN 07296-2019 and 07514-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190001-EI 10/16/2019 PSC-2019-0426-CFO-EI
Order PSC-2019-0426-CFO-EI granting TECO’s request for confidential classification and motion for protective order (of DN 09112-2019) for a period of 18 months from the date of this order.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20190110-EI 10/16/2019 PSC-2019-0427-CFO-EI
Order PSC-2019-0427-CFO-EI granting Duke Energy’s motion for temporary protective order (DN 08121-2019).
Petition for limited proceeding for recovery of incremental storm restoration costs related to Hurricane Michael and approval of second implementation stipulation, by Duke Energy Florida, LLC.
20190156-EI 10/16/2019 PSC-2019-0428-CFO-EI
Order PSC-2019-0428-CFO-EI granting FPUC’s motion for temporary protective order (DN 08824-2019).
Petition for a limited proceeding to recover incremental storm restoration costs, capital costs, revenue reduction for permanently lost customers, and regulatory assets related to Hurricane Michael, by Florida Public Utilities Company.
20190136-EI 10/15/2019 PSC-2019-0412-CFO-EI
Order PSC-2019-0412-CFO-EI granting TECO’s request for confidential classification and motion for protective order (of DN 05265-2019) for a period of 18 months from the date of this order.
Petition for a limited proceeding to approve third SoBRA, by Tampa Electric Company.
20190136-EI 10/15/2019 PSC-2019-0413-CFO-EI
Order PSC-2019-0413-CFO-EI granting TECO’s motion for temporary protective order (DN 08606-2019).
Petition for a limited proceeding to approve third SoBRA, by Tampa Electric Company.
20190136-EI 10/15/2019 PSC-2019-0414-CFO-EI
Order PSC-2019-0414-CFO-EI granting TECO’s motion for temporary protective order (DN 07459-2019).
Petition for a limited proceeding to approve third SoBRA, by Tampa Electric Company.
20190136-EI 10/15/2019 PSC-2019-0415-CFO-EI
Order PSC-2019-0415-CFO-EI granting TECO’s motion for temporary protective order (DN 08749-2019).
Petition for a limited proceeding to approve third SoBRA, by Tampa Electric Company.
WATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20190118-WU 10/18/2019 PSC-2019-0429-PCO-WU
Order PSC-2019-0429-PCO-WU suspending Lighthouses’ proposed final rates; docket to remain open pending Commission’s final action on proposed final rates.
Application for increase in water rates in Gulf County by Lighthouse Utilities Company, Inc.